Stay tuned for our monthly news!

Stay informed

No, thanks

ada

Article27 Nov 20268 min read

How long does CE marking take under MDR after FDA clearance?

How long does CE marking take after FDA clearance? 82% of notified bodies report 13-24 months under MDR. What the 2027 caps change and what they do not.

Summary

  • How long does CE marking take? Plan on 13 to 24 months after the written agreement. That is the range 82% of responding notified bodies reported for a new quality system plus product certificate under Regulation (EU) 2017/745, the Medical Device Regulation (MDR), in a European Commission survey with data as of February 2026.
  • FDA clearance earns no discount in Europe. The average 510(k) took about 141 days for the FY2025 cohort, in US Food and Drug Administration (FDA) data through June 2026. Europe asks for its own file and takes three to five times as long.
  • Half the clock is yours, on both sides of the Atlantic. In Commission-funded surveys with data to October 2024, notified bodies put 56% of the time on manufacturers. The FDA's figures give the submitter about 66 of those 141 days.
  • The 2027 caps discipline the notified body, not you. From February 25, 2027, Implementing Regulation (EU) 2026/977 caps notified-body phases at 30, 120, 90 and 20 days, about 170 days with audit and review in parallel under Annex IX. The clock stops while you answer, and earlier agreements are excluded.

How long does CE marking take under the MDR after FDA clearance?

In a European Commission survey with data as of February 2026, 82% of responding notified bodies reported 13 to 24 months from the written agreement to a new quality management system (QMS) plus product certificate. Preparation comes on top: 6 to 12 months was the most common answer among manufacturers in a Commission-funded survey with data to October 2024. FDA clearance alone shortens neither phase.

Europe is not slow out of malice. It is slow by design, and design, unlike malice, can be planned for.

Except for most self-certified Class I devices, an independent notified body must assess a device before it carries the CE mark. In February 2026, 52 held an MDR designation, and many belong to Team-NB, the European Association of Medical devices Notified Bodies.

The Commission's survey, run by the Austrian National Public Health Institute (GÖG), Areté and Civic Consulting, shows a crowded middle and a long tail:

82% of notified bodies report 13 to 24 months from agreement to certificate

New MDR QMS plus product certificate: time from written agreement to issue, % of the 39 notified bodies with data, February 2026

6 to 12 months 8% 13 to 18 months 51% 19 to 24 months 31% More than 24 months 10% 82%

Source: European Commission notified-body survey by GÖG, Areté and Civic Consulting, data as of February 2026.

A QMS-only certificate moves faster: 94% of notified bodies reported 18 months or less, against 59% for QMS plus product. It is the product review that stretches the calendar.

From the other side of the table, MedTech Europe, the European medical technology industry association, surveyed 138 device manufacturers in April and May 2024 and found average times of 19.5 months for the quality system and 21.8 months for technical documentation. The market has drawn its own conclusion: among large manufacturers, the share launching first in the EU fell from 72% before the MDR to 39%.

Washington, meanwhile, kept its pace with fewer hands. The FDA lost about 21% of its workforce between September 2024 and January 2026, MedTech Dive reported in April 2026. Yet the average 510(k) decision time held at about 141 days for the FY2025 cohort.

A 510(k) clearance, however, is not a passport: the EU demands its own file and its own audit, as we explain in 510(k) vs CE Marking: Why FDA Clearance Does Not Carry Over to Europe.

Why do CE timelines slip?

CE timelines slip because companies plan the notified body's clock and ignore their own.

The usual plan is a comfortable fiction: take the fastest quote, start the clock at submission and let the notified body set the pace. It breaks in four places.

The clock is shared. In surveys with data to October 2024, MDR manufacturers put 55% of the time from agreement to certificate on notified bodies, and notified bodies put 56% on manufacturers. Both cannot be right. The FDA's ledger, which measures rather than asks, suggests the truth sits near the middle: about 76 of the 141 days in the FY2025 cohort were FDA days and about 66 the submitter's.

On both sides of the Atlantic, close to half the clock belongs to the applicant

Share of the time to a decision, by side. US: measured days, FY2025 510(k) cohort. EU: each side's own estimate in surveys with data to October 2024, from written agreement to certificate.

US 510(k), FY2025 cohort FDA 54% (~76 days) Submitter 46% (~66 days) EU, as manufacturers see it Notified body 55% Manufacturer 45% EU, as notified bodies see it Notified body 44% Manufacturer 56%

Sources: FDA MDUFA performance report, data through June 2026, US shares computed by CW1; Commission-funded surveys by GÖG, Areté and Civic Consulting, data to October 2024.

The notified bodies' own files are less diplomatic. In February 2026, only 14 of 52 said that more than half of the submissions they receive are complete, and incompleteness made up a quarter of the reasons they gave for refusing applications. File quality and response speed are your half of the clock, and only you can shorten it.

Clinical evidence is where certificates stall. In MedTech Europe's April to May 2024 survey, half of device respondents had at least one certificate significantly delayed or closed negatively because the notified body challenged the clinical evaluation. A 510(k) built on substantial equivalence often lacks the clinical depth the MDR expects.

The queue stays crowded through 2028. Under Regulation (EU) 2023/607, legacy devices that met its conditions may stay on the EU market until the end of 2027 or 2028 while their MDR files are assessed. Those files compete with yours for the same reviewers.

The 2027 caps time only one side of the table. Implementing Regulation (EU) 2026/977, adopted on May 4, 2026, caps the four notified-body phases at 30, 120, 90 and 20 days from February 25, 2027. Under Annex IX of the MDR, the audit and the product verification run in parallel, so the notified body's own days top out at about 170. On paper, the rest is clock-stop time, though the regulation itself foresees limits lapsing. The clock stops the day the notified body asks you a question and restarts the day after you answer, up to four times each in audit and verification, plus two more per additional site audited. Waits for an expert panel or the European Medicines Agency do not count, and your time to answer can be extended only if justified and agreed in writing. None of it applies to agreements signed before February 25, 2027.

How do you build a CE timeline a CFO can fund?

Build it as a range with a buffer and a named owner for every day that is yours, because a CFO can fund a range but not a hope.

  1. Plan preparation as its own phase. It sits outside the survey clocks, and about half of manufacturers needed over a year in data to October 2024. From application to agreement, 65% of cases took under two months in the Commission's February 2026 data.
  2. Set a base case and a stress case. Take 18 months after the agreement as the base case, the top of the band 51% of notified bodies report, and 24 months as the stress case. Add 6 to 12 months of preparation and two to reach the agreement, and by our arithmetic a standing start becomes 26 to 38 months, longer if preparation runs past a year. Fund the stress case: one notified body in ten reports longer.
  3. Gap-assess the FDA file before you apply. Map your 510(k) file to the MDR technical documentation, starting with clinical evaluation, post-market surveillance and labeling. Every gap closed before the agreement is a question the notified body never has to ask.
  4. Put a deadline on your own answers. Each notified-body question stops its clock and starts yours. Name one owner per question, set an internal deadline and track your days as closely as theirs.
  5. Decide when to sign. Only agreements signed from February 25, 2027 get the caps, so model both dates against your notified body's queue.
  6. Fund milestones, not a date. Release budget at the agreement, the closed QMS audit, the closed technical review and the certificate. We price the stress case in How Much Does CE Marking Cost for an FDA-Cleared Medical Device?

Set against the 510(k), the European averages look like this:

MDR certification averages run four to five times as long as a 510(k)

Months to decision or certificate. FDA: submission to decision. EU averages: reported by manufacturers. EU band: notified bodies, from written agreement. Dashed lines: 18-month base case and 24-month stress case after the agreement, preparation excluded.

Base case 18 Stress case 24 FDA 510(k) average, FY2025 4.6 months (141 days) EU QMS assessment average, 2024 19.5 months EU technical file average, 2024 21.8 months 82% of notified bodies, Feb 2026 13 to 24 months 0 6 12 18 24 30 months

Sources: FDA MDUFA performance report, data through June 2026, 141 days converted to months by CW1; MedTech Europe survey, April to May 2024; European Commission notified-body survey, data as of February 2026.

A runway built this way is rarely early. It is, however, fundable, and in Europe that is the virtue that counts.

What controls each phase of the CE mark timeline in 2027?

Notified body review time is capped for agreements signed from February 25, 2027, but only one phase is fully yours, two are shared and two sit mainly with the notified body.

Phase

Reported duration or legal cap

Source id

Who controls it

How to shorten it

Dossier preparation

6 to 12 months most often reported, data to October 2024

R1-20: GÖG survey

Manufacturer

Gap-assess the 510(k) file first

Application review and written agreement

30 notified-body days from February 25, 2027; under 2 months in 65% of cases, February 2026 data

R1-24: EU 2026/977; R1-10: Commission survey

Notified body, on a complete application

Send a complete application and sign fast

QMS audit

120 notified-body days from February 25, 2027, clock stops excluded; 19.5 months elapsed on average, April-May 2024 survey

R1-24: EU 2026/977; R3-21: MedTech Europe

Shared

Run a mock audit against MDR requirements first

Technical documentation assessment

90 notified-body days from February 25, 2027, in parallel with the audit; 21.8 months elapsed on average, April-May 2024 survey

R1-24: EU 2026/977; R3-21: MedTech Europe

Shared

Answer each question within your internal deadline

Certification decision

20 notified-body days from February 25, 2027

R1-24: EU 2026/977

Notified body

Close every open finding before the decision

FDA 510(k) benchmark

About 141 days average total time, FY2025 cohort, data through June 2026

R3-12: FDA performance data

FDA and submitter

None; a benchmark, not an EU proxy

How CW1 helps

CW1 Group starts with the half of the clock that is yours: an audit of your FDA file, your quality system and your cash runway. We then design the EU strategy, from the choice of notified body to the order of markets, and prepare the path to the written agreement. Our consultants and doctors carry out the first regulatory and financial work alongside your team. Then we step back, and your team carries on.

Frequently asked questions

How long does a CE mark take after FDA clearance?

For a new QMS plus product certificate, 82% of responding notified bodies reported 13 to 24 months from the written agreement, in the European Commission's survey with data as of February 2026. Preparation comes on top, and FDA clearance alone shortens neither.

Why do notified bodies take so long to issue MDR certificates?

Part of the time is theirs and part is yours: in surveys with data to October 2024, notified bodies put 56% of the time on manufacturers. In February 2026, only 14 of 52 notified bodies said most submissions reach them complete.

Will the 2027 EU notified body deadlines make CE marking faster?

Only partly: for agreements signed from February 25, 2027, Implementing Regulation (EU) 2026/977 caps notified-body phases at 30, 120, 90 and 20 days, but the clock stops while you answer. The Commission's December 2025 proposal to simplify the MDR was still being negotiated in August 2026, so it belongs in no budget.

What is the average MDR certification timeline for the QMS and the technical file?

MedTech Europe's April to May 2024 survey reported averages of 19.5 months for the quality system and 21.8 months for technical documentation.

Is FDA 510(k) review faster than MDR certification?

Yes, by a wide margin: the average 510(k) took about 141 days for the FY2025 cohort, in data through June 2026.

More insights

We use cookies to give you the best possible experience, and while some are essential, others help us understand how you use the site, so we can improve it. Click “Accept all cookies” to proceed as specified, “Decline optional cookies” to accept only essential cookies, or click “Manage my preferences” to choose what cookie types you will accept. Cookie Policy.

© CW1 Inc, All rights reserved
CW1 Group